| Proposed Tentative Construction and Renovation Timeline |
| July/August 2009 |
Demolish Hensel T& U and begin Phase I construction |
| November/December 2009 |
Installation of additional exterior lighting for Collge View and Hensel |
| February thru March 2010 |
Installation of DSL in College Avenue, College View, Hensel and Avenue A |
| March thru July 2010 |
Renovation of Hensel X, Y & Z (gas to electric conversion) |
| June and July 2010 |
Renovation of College View (gas to electric conversion) |
| July 2010 |
Installation of furniture in Hensel V, W, X, Y & Z |
| July 2010 |
Installation of furniture in College View and Avenue A |
| July/August 2010 |
Demolish College Avenue 1 - 11 and begin Phase II construction |
| August 2010 |
Open Phase I (250 apartments) |
| July/August 2011 |
Demolish Hensel V & W and begin Phase III construction |
| August 2011 |
Open Phase II (200 apartments) |
| July/August 2012 |
Abandon College Avenue 12 - 16 |
| August 2012 |
Open Phase III (150 apartments) |